Those of you still in the market for a modular home will find this article by Al to be very descriptive of the project schedule you should expect and why a preliminary schedule is so important to your success. I say "still in the market" because given the state of the housing market, with prices continuing to fall, the glut of homes on the market and the fact we have not reached the bottom, your choices are wide open.
MODULAR HOMES 101
Article Five
How Do I Get There
From Here?
The time process you must endure from purchasing a modular
home to living in it is a journey.During that journey you will face many issues
and make many decisions.That is why I
highly recommend that anyone contemplating this year-long experience, hire a
professional consultant.One who is
knowledgeable in the modular home industry to act as your guide, teach you
elements of the process and act as your advisor.
I decided to title this article, “How Do I Get There From
Here?”I chose that title because most
of us would be utterly lost during this journey without assistance.You as the buyer/owner not only need
direction, but you also need tools.All
of us need tools to accomplish objectives and goals.Two tools I believe are most important for
understanding, keeping track and verifying activities along the journey are the
preliminary schedule and the preliminary budget.
This article will present information on the preliminary project
schedule.The following article, Article
Six, will present information on the preliminary project budget.
The Tentative Project
Schedule
Before a project schedule can be created, a consultant familiar with modular
homes should be able to assist you with a work breakdown.A work breakdown is the first step in preparing
a schedule.This is a list of work
activities necessary to meet the owner’s expectations and the legal
requirements of the local government.You as the owner may have wide ranging interests from aesthetics to
functions, but the local government is mostly concerned about occupant’s health
and life safety issues.Once a work list
is prepared an estimate of the amount of time for each work task is required.
When the work effort described as various tasks is joined with the time
period necessary to complete these tasks a schedule will have been
generated.The schedule dates must be as
realistic as possible and must be acceptable to the contractors doing the
work.If those dates do not have a ‘buy-in’
by the people (contractors) doing the work, the schedule will be inaccurate and
will be worthless to the contractors and you.Therefore, the schedule must be as true to the actual time that it takes
to conduct a task as possible.
As Wikepedia states, “In many industries, such as engineering and
construction; the development and maintenance of the project schedule is the
responsibility of a full time scheduler or team of schedulers, depending on the
size of the project.In your situation,
your schedule is miniscule when compared with large projects, but just as
important.The thoughtful and careful
preparation of the schedule cannot be underestimated.
Many project scheduling software products exist which can do much of the
tedious work of calculating the schedule automatically and plenty of books and
tutorials are dedicated to teaching people how to prepare schedules. However,
before your consultant can use these tools, he or she should thoroughly
understand the concepts behind scheduling.This is the real key to planning a successful project.
As I said above, the schedule is a tool.It must be thought of as tentative because it
may be subject to immediate and frequent change.Changes to schedules are usually caused by
external factors over which you have no control.One example that quickly comes to my mind is
pouring concrete.Here in southern California one might
prepare a schedule for a construction project and show a concrete pour for
February 15th.A few days
before that date you order several ‘redi-mix’ trucks of concrete to the
site.A day or two before that pour date
a storm blows from the Pacific Ocean and pours
rain for several days, including the fifteenth of the month of February.Unless you make other arrangements, the ‘redi-mix’
trucks will not deliver concrete to construction sites.Because of the rain your schedule will need
to be updated.Note; I’m told that in
Seattle, Washington trucks would be sent to the construction site regardless of
the weather.The obvious point is that
there may be, “acts of nature,” that do not permit you and others to follow the
schedule precisely.That is the reason
one must always consider a project schedule to be a ‘tentative’ schedule and
always subject to change.
A Preliminary Schedule
May Take Many Forms
There are many types of schedules.Word schedules, bar chart schedules, critical
path schedules and on and on.The
simplest schedule I believe is a word schedule.That is what I am presenting herein because I believe it to be rather
simple and a good place for the uninformed to start.
Your schedule should fit your thinking process in order for
it to be a useable tool.This is not an
attempt to teach you about psychology, but only to give you a meager idea of
how you might think about time and space.
Thanks to Wikepedia we find that research by Child
Development Theorist, Linda Kreger Silverman who suggests that less than 30% of
the population strongly uses visual/spatial thinking, another 45% uses both
visual/spatial thinking and thinking in the form of words, and 25% thinks
exclusively in words. According to Kreger Silverman, of the 30% of the general
population who use visual/spatial thinking, only a small percentage would use
this style over and above all other forms of thinking, and can be said to be
'true' "picture thinkers."
People think quite differently?In my not so humble opinion the vast majority
of us are some combination of all three of the above categories.The prospective modular owner should give
some thought as to how he/she thinks because this may determine which type of
schedule goes best with his/her thought process and is most meaningful.
Preparing a
Preliminary Schedule
Dates show the estimated beginning date and the estimated
ending date of each significant piece of work.If an activity takes only one day, such as submitting a site plan to the
building department or paying a fee, then there will only be one date, the date
that activity is supposed to take place.You will have to determine your own beginning and ending dates for your
best guess of activities for your project.For example, (see # 3 below) imagine that it takes the Septic Contractor
three work days to dig a tank hole and trenches for pipes and leach field,
place the tank, connect all pipes, install the leach field and backfill
everything.Then you will have a start
date, such as 8/10/YR and a completion date, such as 8/13/YR.
As an example, one line of your schedule may look like this:
8/12/YR-8/15/YRSeptic Contractor Installs Tank and Leach
Field
For the purpose of this exercise I will not include
completion dates, so as to simplify the presentation of the schedule and
because the time allotted for an activity may change significantly from project
to project.The preliminary schedule
below will give you a general idea of the progression of activities by only
showing start dates and then activities.
Example of a
Preliminary Schedule
1. 5/1--Owner signs an agreement with a knowledgeable
consultant for services to be
performed throughout this process
2. 5/3--Owner deposits money with title company for purchase
of modular home
3. 5/6--Purchase order submitted to modular manufacturer
4. 6/1--Data gathering regarding legal ownership, legal lot,
easements, etc. for site
5. 6/15-Licensed land surveyor surveys site and prepares
legal site plan and plot plan
6.
7/1--Manufacturer starts construction of modular home at factory
7. 7/29-Soils engineer visits site and prepares soils test
(independent agreement with
owner and soils engineer)
8. 8/8--Site
plan, foundation plan, and floor plan for modular home submitted to local government
building department and various fees paid (other fees will follow as required
such as building permit fee and school fees)
9. 8/10-Septic
contractor obtains permit and installs tank and leach field (independent agreement
with owner and septic contractor)
10.
8/16-Consultant prepares bid documents for general (site) contractor, owner
approves documents
11.
9/1--Consultant provides bid documents to general contractors
12.
10/1-Consultant meets with owner to review bids, select general contractor, and
contract signed by all parties
13. 10/15-A
good faith deposit is provided to general contractor to reserve a start date
14. 10/25-General
contractor moves onto site, grades pad, digs footing trenches and installs rebar,
etc. etc.
15. 10/30-Local
government inspector inspects footings and placing of rebar
17. 11/4--General contractor begins work for franchise and
non-franchise utilities to
the
site and upon the site property
18. 11/29-Factory completes modular home
19. 12/2--Factory representative, consultant and owner conduct
a ‘walk through’ of
modular at the factory and prepare a
punch list
20. 12/5--Factory
makes corrections per punch list
21.12/6--Modular house is moved to site
22.
12/7-Modular house arrives at site andis
moved into place over footings
23.
12/7-Modular house is allowed to settle for 5 to 7 days
24.
12/12-General contractor closes house and connects utilities
25. 12/13-Local
government inspector inspects all Activities to date
26. 12/14-Roof
setup, block and level house
27. 12/15-Concrete
contractor installs steps and stem wall (independent agreement with owner and
concrete contractor)
28. 12/16-Drywall
close-up, repair, tape and texture inside, paint,
carpet installation, adjust doors and install fixtures and equipment
29. 12/27-Connect
and check fire sprinkler system (note: in San Diego County every new home must
have a complete and functioning inside fire sprinkler system before an
occupancy permit is issued.)
30. 1/15-Local
Government inspection of a completed and working fire sprinkler System (note: an
inspection may also be required at the factory before
the modular is moved
into your local jurisdiction.)
31.
1/20-General contractor to provide all special or extra work as contractually
required
by owner
32. 1/30-Heating,
ventilation, air conditioning installation by HVAC Contractor
33. 2/20-Final
Inspection by Local Government Inspector
34.
3/1—Occupancy Permit Issued by Local Government, Owner Moves into Modular
End of Schedule
NOTE: THIS IS
NOT A COMPLETE SCHEDULE!
Do not believe
that this schedule is a complete schedule.It is not!I’ve left out
specific items
that might be required due to specific problems or requirements of local
government
codes and ordinances, modifications requested by the owner by the general
contractor’s
contract.This might be the addition of
a retaining wall or some such thing.
Your schedule
might include 100 items or more.But I
have purposefully limited this
schedule for
the readers’ ease of understanding.Schedules
can be very, very
simple or very,
very complex.
Please remember that a schedule is tentative and only a
tool.The purpose of this document is to
educate you about knowing when certain activities take place.Due to things beyond your control those
activities may not occur according to your schedule, so your schedule must be
flexible.It must be easy to change and
it must not cause you to believe it rules all activities, because it does
not.So, why have one?It is an invaluable tool to help you keep
track of things since it is virtually impossible to keep all these things in
your head.
Once the project manager develops an understanding of the
usual timeline for most housing types, it would seem the schedule could be
easily put together and provided to the owner.Scheduling information becomes more accurate and valuable with use.Since you, as owner, may not have done
scheduling before, you must rely on your consultant to assist you
One might ask, “Is the site contractor on schedule?”This is a difficult question to answer.If “acts of nature” enter the picture, such
as storms, rainfall, snowfall and other such uncontrollable things someone must
determine how much and to what extent the schedule has changed.This too may not be an easy issue to resolve
between the consultant/owner and the contractor.A contract with a general contractor should
have, among many other things, a start date and a completion date.Any delay during the construction will cause
the completion date to change.This new
date is usually negotiated with the general contractor.
Whether a schedule is written words or in some form of
graphic chart it should show major and some minor work tasks and all should be
related to some realistic time line.It
is inevitable that the schedule will change during the course of the
project.
It is a serious mistake to launch into a project without a
preliminary schedule.
9/3/2008 4:02 PM
LJ wrote:
Hmmm. Did that. You failed to mention the part where they promised that the house was the same as a stick built house. Per the housing agencies I dealt with only today, this is a big "no no" when selling a product, especially when FHA, FEMA, and HUD are involved. Finally today, I hit pay dirt. You can't deal with a company, like Champion/Genesis/Redman that lies. Thank God for independent parties, our Attorney General, and local prosecuters. Today was my breaking poing. Now, I don't just want to be made whole. I want compensation for the fraud, concealment, cooersion, colusion, and for what we've had to endure. I've never spoken before our government, but plan to tell the truth, the bad and the ugly. There is no good. This has been hell and it seems that Champion finds a market in survivors of natural disasters. Punitive damages are in order. You give someone enough rope to hang themselves (which they are obviously quite accomplished at) and if they take too long we have to be prepared to kick the chair. All together now... Reply to this
9/4/2008 5:48 AM
L.J. wrote:
Just to clarify, just so there isn't any question...we are Cedar Fire rebuilders from 2003. In Ocotober, this will make five years. Following a "time line" for proper set up doesn't quite touch on our experience. I find it insulting. Our water heater is on the second floor. Water heaters are not supposed to be on the second floor, period. The risk of fire is GREAT! It is set directly on the ground, not 18" inches as required. The water heater blows out at least five times per day. If you are TRYING to wash a load of laundry, good luck. We have a Kenmore HE washer, a front loader. In order to wash a load of laundry each load must be run a minimum of three times. Cold water doesn't clean laundry. We are using and astronomical amount of water with the bills to boot. With the water heater not being the right water heater in the first place, it sucks the propane in exponential amounts. The filled tanks cost $800 per fill up. The water heater makes horrible clunking noises, I'm talking loud, when lit. I was told to find someone to put a water heater in. I did. It's a tankless. There isn't anywhere else for the thing to go, so it HAS to be tankless. Otherwise, we are talking about placing a water heater in an outbuilding on with a slab to support it beside our "house" at an incredible expense. If you think you electrical panel will support your water heater, think again. Our panel needed to be upgraded to support it. It has blown our washing machine out twice in six months to where we needed a completely new electrical part and it happened again on Sunday. Same problem, same part. So, we live in the mountains of California. We are a good thirty minutes from the nearest "town" and there wasn't anyone that would up the mountain to install a water heater, electrical, and to remove the dangerous water heater that is upstairs in my daughter's bedroom. We moved in to our Cedar Fire rebuild a year ago. She hasn't been able to use her bedroom For any of you parents out there, take note. She is a brain injury survivor to boot. I was told by Barbara Holloway and Cliff Blendon(sp?) that if I were to find a licensed plumber, they would pay for the removal of the old water heater and installation of the new one. The electrical doesn't support my washer as it is, so that HAS to be corrected. I spent June, July, and August trying to find someone to do this job. I finally found ONE that agreed to help us. We submitted the bill to Champion in AZ and have yet to hear from them. We were supposed to open a home day care in January of 2008. Without a safe environment, we can't pass the home inspection for the license. We are losing a minimum of of $3600 per month, with most likely a five child income of $4500. We have sold everything we have to sell. We will likely lose our home in two months. They won't call us back. When told of the problems with the wiring that trapped us in our home during the Witch Fire, Barbara Holloway literally laughed at us. Very funny, lady. Reply to this